Roseville Rail Yard Tunnel Repair
Emergency structural repair of a failing rail tunnel crown in one of the West Coast's busiest rail yards.
Project Stats
Services Used
The Problem
Routine inspection revealed significant delamination of the tunnel crown with active spalling creating a safety hazard. The tunnel carries 40+ trains daily and complete closure was not feasible. Repair had to occur in 2-hour nighttime windows.
Our Approach
Rock Supremacy developed a rapid-deployment system using pre-fabricated steel sets and quick-setting shotcrete. Crews worked in coordinated 2-hour blocks, installing systematic support and applying shotcrete in alternating sections.
The Outcome
All repairs were completed in 6 weeks without any unplanned service disruptions. Load testing confirmed the rehabilitated sections exceed original design capacity.